Process order and cycle times...
關於此模型
Process order and cycle times (TC):
Receiving (Recebimento) — TC = 1 min Hopper (Moega) — TC = 0.6 min Roaster (Torrador) — TC = 8.75 min Resting Silos 24h (Silos 24h) — TC = 1440 min Blender (Blendador) — TC = 2 min Grinder (Moedor) — TC = 6.5 min Packaging (Empacotamento) — TC = 7.5 min Storage (Estocar) — TC = 0.5 min
"Process order and cycle times..." is a public Machinations diagram shared in the Community by hugo matias, with 29 components.