此頁面有繁體中文版本。

This page is also available in English.

Process order and cycle times...

Diagram: Process order and cycle times...Diagram: Process order and cycle times...

关于此模型

Process order and cycle times (TC):

Receiving (Recebimento) — TC = 1 min Hopper (Moega) — TC = 0.6 min Roaster (Torrador) — TC = 8.75 min Resting Silos 24h (Silos 24h) — TC = 1440 min Blender (Blendador) — TC = 2 min Grinder (Moedor) — TC = 6.5 min Packaging (Empacotamento) — TC = 7.5 min Storage (Estocar) — TC = 0.5 min

"Process order and cycle times..." is a public Machinations diagram shared in the Community by hugo matias, with 29 components.

It was created in 2026年8月 and last edited in 2026年8月.

Open the diagram in the Machinations app and press Play to watch the resources move, adjust its values to test how the system responds, or remix it to make an editable copy in My diagrams.

更多来自 hugo matias